Level of Development (LOD)

Level of Development (LOD)

What is Level of Development

The level of development or LOD is a means to define the required contents of a Building Information Model (BIM) to deliver on the various project deliverables at each stage of the project from concept through to post occupancy.

The below table outlines the typical stages of development for LOD
(Table 1 - NATSPEC BIM Paper: BIM and LOD).

The problem with this metric is that a linear level of modelling detail does not align with producing and delivering on the actual project deliverables over the various stages of a project lifecycle.

Example:

Do we really need fabrication Level of Development for As-built in terms of using it for Facilities & Asset Management? We may only care about knowing where the element is and all the asset information/specifications and less about having every little nut, bolt, washer and detail that would be needed to fabricate it. It’s already built and no longer a coordination problem.

This misconception often results in BIM being specified at too high level of development, and rendering it too costly or the model being so heavy with detail it becomes unusable.

The NATSPEC BIM LOD Paper clearly describes this misconception with the below diagram providing a good example:

LOD 100:

A photorealistic image of a chair is selected purely for the purposes of a rendering. Even if detail information is associated with it, it is not assumed to be relevant at this stage.

LOD 200:

A generic model of a chair is selected for the purposes of a furniture layout even though a decision about the actual chair has not been made yet. The important thing is the nominal floor space allowance it represents.

LOD 300:

During documentation a simple placeholder that helps minimise model file sizes is selected. The chair may appear in schedules or be used for costing but is not expected to be used for ordering.

LOD 400:

A chair with a specific manufacturer and model number is selected for ordering purposes.

LOD 500:

The chair has a manufacturer, model number, supplier, serial number and date of purchase, but its image, EG: A photograph, may not necessarily be included in the model.

A much less appropriate and less ambiguous approach is to break the Level of Development down into 2 separate categories Level of Detail (LOD) and Level of Information (LOI).

Level of Development vs Level of Detail vs Level of Information

At each stage of the project life cycle as appropriate to the applicable Plan of Work for each Element category an appropriate Level of Detail and Level of Information should be defined to deliver on the Project BIM requirements.

Standard

Pre-Design

Design

Construction

Handover

In Use

End of Life

Standard

Pre-Design

Design

Construction

Handover

In Use

End of Life

RIBA (UK)

0

1

2

 

3

4

5

6

7

 

Strategic Definition

Preparation and Brief

Concept Design

 

Developed Design

Technical Design

Construction

Handover & Close Out

In Use

 

ACE (Europe)

0

1

2.1

2.2

2.3

2.4

3

 

4

5

Initiative

Initiation

Concept Design

Preliminary Design

Developed Design

Detailed Design

Construction

 

Building Use

End of Life

AIA (USA)

 

 

 

 

 

 

 

 

 

 

 

Schematic Design

 

 

Design Development

Construction Documents

Construction

 

 

 

APM (Global)

0

1

2

 

3

4

5

6

7

 

Strategy

Outcome Definition

Feasibility

 

Concept Desgin

Detailed Design

Delivery

Project Close

Benefits Realisation

 

Spain

 

 

 

 

 

 

 

 

 

 

 

 

Proyecto Básico

 

 

Proyecto de Ejecución

Dirección de Obra

Final de Obra

 

 

NATSPEC (Aus)

 

 

 

 

 

 

 

 

 

 

 

Establishment

Concept Design

Schematic Design

Design Development

Contract Documentation

Construction

 

Facility Management

 

NZCIC (NZ)

 

 

 

 

 

 

 

 

 

 

 

Pre-Design

Concept Design

Preliminary Design

Developed Design

Detailed Design

Construct

 

Operate

 

Russia

 

 

 

 

 

 

 

 

 

 

 

 

AGR Stage

Stage P

Tender Stage

Construction Documents

Construction

 

 

 

South Africa

 

1

2

3

 

4

5

 

 

 

 

Inception

Concept and Viability

Design Development

 

Documentation

Construction

Close Out

 

 

Table 2: Comparison of International Plans of Work

Level of Detail (LOD)

The Level of Detail is used to define at what level the 3D modelling aspects should be completed to and the required accuracy of that modelling. BIM Uses may include:

  • 3D Coordination & Clash Detection

  • Construction Sequencing (4D)

  • Cost Estimation / Quantity Take-off (5D)

  • Visualisation

  • Solar / Energy Analysis, etc.

Level of Information (LOI)

The Level of Information is used to define at what level the metadata aspects associated to the model are to be completed, such as what parameters to include and how to populate them.

  • Structural Analysis

  • Services Analysis

  • Solar / Energy Analysis

  • Cost Estimation / Quantity Take-off (5D)

  • Asset & Facilities Management

Deciding on the appropriate LOD

The level of development for every project undertaken within Revit should be carefully considered before any work commences. Each project will have its own unique set of deliverables suited to the level of documentation required. It should never be considered that just because it is in Revit that everything should be 100% modelled with information appended either.  That said, with a quality library and efficient team the difference in effort to produce a lightweight LOD 200 model vs LOD 350 model can be minimal.

The Level of Development should be agreed upon for all elements and phases, and form part of the BIM Management Plan (BMP/BEP).  This will ensure that resources are optimised for the outputs required.  It is usually dictated by how the model will be used both during the design, construction and post occupancy phases.

For example, will it be used for:

  • 3D Coordination / Clash Detection

  • Construction Sequencing (4D)

  • Cost Estimation / Quantity Take-off (5D)

  • Visualisation (Renderings / Animations / Augmented Reality / Virtual Reality / Mixed Reality)

  • People & Vehicle Flow Simulations

  • Code Validation

  • Safety Planning

  • Structural Analysis

  • Services Analysis

    • Fire

    • Fuel

    • Security

    • Electrical

    • Hydraulic

    • Mechanical

    • HVAC

  • Lighting Analysis

  • Solar / Energy Analysis

  • Fabrication

  • Field BIM

  • Site Planning

  • Space Planning

  • As-Built verification

  • Asset & Facilities Management

    • Sensor Integration / Digital Twin / Systems Analysis

Each of these uses all have their own specific requirements depending on the project phase and desired accuracies, as such it is important to discuss this as early in the project as possible with the client and project team.

Model Element Authors

Beyond the LOD & LOI, it is important to define the model element authors (MEA) for each element at each stage. That is, who is actually responsible for creating the modelled element or populating the data to the required level.

Once you know the LOD/LOI and MEA for the given project stage and for each element type you can commence modelling your building in Revit.

In some cases and project stages, elements may have a split MEA. For example, for a Structural Slab, the architect will inform the footprint/extent of the slab, but the structural engineer is responsible for it’s thickness, material and acceptable penetrations, beams etc.